[Untitled]‎ > ‎

Penzance Harbour Options Shortlist Announced

posted Dec 22, 2011, 1:22 PM by Richard Cliffe

The Penzance Harbour Scheme Management Board has revealed its 3 options (out of 15) to be worked up in more detail for Feb 2012.  One of the 3 options is an ambitious Albert Pier option.

 The decision was taken by the PHSMB not to set thresholds for meeting cost and programme (time) limits, instead ambitious options were just scored lowly under these headings.    As a result options have not been eliminated because they appear unlikely to meet cost or programme constraints.   This may prove to be an issue when the Albert Pier option is worked up in more detail.  The other two shortlisted options are significantly lower risk.

 The Hyder Consulting report is available under “files” (Pz Harbour Short-List Report – Dec 2011)

 

Comments